Mineral Resources 20 Walters Drive

Mineral Resources 20 Walters Drive, Osborne Park

Kwikcut was engaged by MRL to complete more than 1100m2 of concrete removal over 12 x levels of their new office building in Osborne Park.

Details:

  • We commenced work on-site, installing crash decks over multiple levels to allow the safe removal of 300mm – 400mm thick concrete slabs.
  • All the concrete removal was strategically planned, utilising both day and night shifts to ensure the prompt completion of the project.
  • The penetrations varied in size from 6m2 up to 90m2 and were removed via gantry crane after the sawing and core drilling works had been completed.

Highlights:

  • Running day shift and night shift prior to 16th January deadline
  • The use of carbon fibre strips reinforce areas of the slab weekend by penetrations.
  • Safe removal of 1100m2 of concrete across 12 levels.
  • Concrete remediation applied to exposed concrete and steel from penetrations.